THE BATTLE TO BUILD THE GORDIE HOWE INTERNATIONAL

With a span of 853m, the Gordie Howe International bridge will be the longest cable stayed bridge in North America. Lucy Barnard finds out why it is being built and the construction challenges it has faced

An analyst report by S&P Global suggested that the project could be delayed by eight months until August 2025
PHOTO: WINDSOR-DETROIT BRIDGE AUTHORITY

In February 2022, a group of Canadian truck drivers, angry about covid vaccine mandates, parked their vehicles across a stretch of road leading to North America’s busiest border crossing and waited.

For almost a week, truckers waving Canadian flags stopped traffic from crossing the Ambassador Bridge, which links the metropolitan areas of Windsor, Ontario and Detroit, Michigan, costing the country an estimated US$300 million a day.

The bridge handles around 27% of trade between the US and Canada and the protests highlighted a weak link in the supply chain to Its answer was the US$5.7 billion Gordie Canadian authorities. Howe International Bridge, a 2.5km six-lane, state-owned bridge just a few miles away

Study into alternative crossings

Owned by the influential Mouron family, the suspension bridge is also 92 years old. In 2001, the Canadian government, and others, worried that the ageing bridge would not be able to cope with projected traffic flows, commissioned a study investigating the problems with the border crossing and the infrastructure needed to solve them.

Its answer was the US$5.7 billion Gordie Howe International Bridge, a 2.5km six-lane, state-owned bridge just a few miles away from the Ambassador Bridge, and which is currently being built linking the Interstate 75 in Michigan, US with Highway 401 in Ontario, Canada.

Named after Canadian ice hockey player and Detroit Red Wing’s star, Gordie Howe, the bridge – expected to be completed in 2025 –

A rendering of what the completed bridge might look like

is set to be the longest cable stayed bridge in North America and is being trumpeted as a symbol of North American unity.

“The design of the Gordie Howe International Bridge serves as a symbol of the unique and vital partnership between Canada and the United States,” says Grant Hilbers, Vice President, Engineering, Windsor-Detroit Bridge Authority, the most senior engineer on the project and the man responsible for overseeing construction of the bridge.

Keen to retain the US$60 million in tolls made each year by the Ambassador Bridge, owner Manuel Mouron spent decades fighting to prevent the Gordie Howe being built until his death in 2020.

Funding for project

Nonetheless, in 2012, after much political wrangling a deal was struck between the Prime Minister of Canada and the Governor of Michigan where the Canadian government agreed to pay for, build and operate the bridge through a public private partnership, while the completed bridge will be jointly owned by Canada and the State of Michigan.

In July 2018 the Windsor Detroit Bridge Authority, the public body charged with masterminding the bridge build, awarded a fixed-price main contract worth US$5.7 billion to Bridging North America, a consortium of AECOM, Dragados, Fluor, Aecon, and ACS, to build, maintain and manage the bridge. Construction started shortly afterwards in October 2018.

Stay cable installation at the US bridge site, January, 2023
PHOTO: WINDSOR-DETROIT BRIDGE AUTHORITY
Michigan interchange, November 2021
PHOTO: WINDSOR-DETROIT BRIDGE AUTHORITY

With each new stage of construction, the distinctive design of this cable-stayed bridge takes shape

One of the first decisions made by Bridging North America was the design of the new bridge. Instead of building another suspension bridge to cross the border, it chose instead to opt for a cable-stayed bridge.

“The cable-stayed bridge design is a modern and elegant form with a tower shape inspired by the curvature of a hockey stick in a slap shot – anod to Gordie Howe,” says Hilbers. Like suspension bridges, cable stayed bridges rely on cables above them for support rather than columns below, enabling the Gordie Howe bridge to be built without the need to build piers in the riverbed – something which would have caused disruption to the busy shipping lanes of the Detroit River.

Although traditionally used for shorter spans than their suspension bridge cousins, over the last twenty years improvements in structural design software have enabled engineers to create longer and more efficient cable stayed bridges, which are generally cheaper and easier to construct than suspension bridges.

With a span of 853 meters (0.53 miles), the Gordie Howe International bridge will be the longest cable stayed bridge in North America when it is completed. Nonetheless, engineers expect it to only be the tenth longest in the world. Russia’s Russky Bridge in Vladivostok, built in 2012, holds the record for the longest at 1,104 meters.

The Gordie Howe International Bridge is designed as a continuous curve, anchored at each end by two inverted Y-shaped towers that suspend the bridge deck via 216 stay cables – 108 on each side.

Choosing a construction method

At first, the team had planned to build the main deck of the bridge using a balanced cantilever construction method which would have involved building the two 220-metertall towers on either side of the river and then building the bridge piece-by-piece outwards until the two 425-meter-long cantilevers met in the middle.

However, by summer 2019 and with the prospect of a hard Detroit winter closing in and bad weather delaying the build, Hilbers and his team decided to change track, opting instead to use a technique called the ‘unbalanced cantilever system’ or ‘stick build.’

This meant that instead of the same level of construction occurring on each side of the tower, Hilbers’ team decided to build the ‘back’ span of the bridge first (the section connecting the pylon with the approach road), with temporary supports that were removed once the cables were installed.

“One of the challenges that the team overcame was the approach to construction of the bridge. Original methods followed the traditional balanced cantilever construction,” he says. “Obstructions in early days, including limited water access, deep soft clay and winter weather lead Bridging North America to re-visit this erection method and select the unbalanced cantilever method for this build.”

Another major technical challenge was digging foundations deep enough to support the bridge’s two 220-meter towers close to the river’s edge.

He points out that a geotechnical survey showed that the ground in the Detroit-Windsor area consisted of layers of lumps of rock, clay and sand, formed during the ice age. In some parts these had cemented together, creating confining layers of impermeable rock, which trapped groundwater.

Moreover, organic debris in the rock also produces hydrogen sulphide gas, a highly toxic, corrosive and flammable gas that smells of rotten eggs and requires workers to take extra precautions.

Uneven ground

To complicate matters further, the ground beneath Detroit-Windsor also contains some of the world’s largest salt reserves and is crisscrossed with salt mines, many of which were excavated as long as a century ago and are either unmapped or poorly mapped. Reports from the 1950s of a large sinkhole opening up and swallowing a warehouse on the Canadian side of the river added to fears that shafts sunk in the wrong location could result in the foundations collapsing.

All of this meant that significant investigations were required to ensure that none of the planned foundations hit a mining cavity and, once the alignment of the bridge had been decided, it could not be changed.

Each of the legs of the two giant inverted Y shaped towers holding the bridge is supported by six shafts which have been drilled into the bedrock to a depth of 36 meters. Then, each of these shafts is filled with approximately 262,000 litres of concrete. The footings are then connected by 1,600 meters of post tensioning cables to create a firm footing.

Other major challenges facing teams have included the covid pandemic, which occurred just as construction work on the bridge was ramping up in 2020, as well the supply chain issues and labour shortages which followed. In June 2023, the Windsor-Detroit Bridge Authority announced that it had appointed lawyer Lindsay Krauss as its third official chief executive officer, taking over from mechanical engineer Bryce Phillips who resigned from the job at the start of the year.

Although officials at the Windsor Detroit Bridge Authority say they continue to target the contractually agreed opening date of 2024, they agree that the timetable could slip. Last year, an analyst report by S&P Global suggested that the project would be delayed by eight months until August 2025. Meanwhile, on the Detroit River, construction works continue. Probably the most noticeable is the two bridge towers, which in summer 2023 had reached 190 meters of their planned 220-meter heights.

Jump-form method

Like most tall tower and bridge projects requiring concrete pours, the towers are being built using a ‘jump-form’ method where teams pour concrete from ready-mix trucks into formwork moulds and rebar and wait for it to set. Then, using a series of support brackets and screw jacks powered by electric motors, the block is slowly lifted to the next level, forming a tower.

Since the start of the year, the team has also been busy installing the thick metal cables which will eventually take the weight of the bridge. So far, 28 of the 216 stay cables have now been installed, each comprising between 38 and 122 metal strands threaded through a high-density polyethylene plastic pipe to protect it from the weather.

“With each new stage of construction, the distinctive design of this cable-stayed bridge takes shape,” says Hilbers. “As the stay cables are installed, the Gordie Howe International Bridge’s inspiring, modern and elegant features will become more visible for residents of Windsor and Detroit.” iC

The bottom of the Gordie Howe International Bridge in Detroit
PHOTO: REUTERS CONNECT
This article appears in September-October 2023

Go to Page View
This article appears in...
September-October 2023
Go to Page View
COMMENT
BEST PRACTICE
NEWS ROUND UP
TOP HIGHLIGHTS ˃ US The state of California
BREAKTHORUGH FOR LONDON'S NEWEST UNDERGROUND TUNNEL
ALL PHOTOS: HERRENKNECHT Construction is currently ongoing in
A STRONG MARKET WITH MORE TO COME
Construction in the US has performed strongly in recent years, with government support and growing sectors such as infrastructure and sustainability-related spending providing impetus, reports Andy Brown
GROWING DEPENDENCE ON INFRASTRUCTURE SPENDING
Government acts have boosted the economy and construction but, with retail and commercial construction under pressure, infrastructure is key, says Scott Hazelton
A SOFT LANDING HOPEFULLY REMAINS
Continued woes in China means global construction equipment demand is weaker than expected but, for most, the slowdown will be gentle and some markets will grow, says Off-Highway Research
CONCRETE'S CARBON FOOTPRINT
Construction work won’t slow down so it’s essential to scale up sustainable initiatives and ways of working with concrete to put the environment first, reports Catrin Jones
Systematically Sustainable
SUSTAINABILITY AS A COMMITMENT AND AN OPPORTUNITY
Cold Milling Machine in the Spor ting Center of the Eternal City
PRECISION ON THE TRACK FOR NEW WORLD RECORDS
A Strong Alliance for Formula 1 Racing
RACETRACK REHABILITATION IN SPA-FRANCORCHAMPS
Battery-Electric Tandem Rollers in the Compact Class
ZERO-EMISSION COMPACTION
Spotlight on Green Technology
LATEST GENERATION PLANT IN SWITZERLAND
Retrofit
The operational service life of asphalt mixing plants
Award-Winning Machines
Prestigious Award for Hamm! The latest HC CompactLine
Digital Ready
This summer, Hamm will be expanding its HD+
Cutting-Edge Technology
The U.S. government commissioned the extension of the
The MINIs Get Off to a Great Start
Discover more online Vögele celebrated the premiere of
DOWNSIZED MACHINES UPSIZED POTENTIAL
The excavator is construction’s most popular machine, known for its agility and versatility. Catrin Jones looks at what could be next in its development
THE COMPETITIV EDGE
Falsework and formwork specialists are focusing on digitisation and sustainability, and tech is the competitive advantage to winning new business, reports
CONSTRUCTION'S AUTOMOMOUS PATHWAY
Construction’s path to autonomy is underway and, while a fully autonomous jobsite is far away on the horizon, the benefits of this technology are being felt today, writes
FUTURE SOLUTIONS
CATRIN JONES speaks to CAROLINA DIEZ FERRER, vice president of future solutions at Volvo CE, on how the OEM is developing solutions to change the way construction uses technology
THE BATTLE TO BUILD THE GORDIE HOWE INTERNATIONAL
With a span of 853m, the Gordie Howe International bridge will be the longest cable stayed bridge in North America. Lucy Barnard finds out why it is being built and the construction challenges it has faced
FIRST IN A SERIES OF RIVER BRIDGES IN CHINA UNVEILED
Zaha Hadid Architects (ZHA) has unveiled the Jiangxi
Looking for back issues?
Browse the Archive >

Previous Article Next Article
September-October 2023
CONTENTS
Page 61
PAGE VIEW