COPIED
6 mins

Lezama’s power plant challenge

How a Spanish demolition contractor drew on 25 years of experience to come up with two dif ferent methods for projects in the energy industry.

After more than 25 years’ experience in the sector and extensive demolition work on chemical plants, industrial buildings and civil works, Lezama Demoliciones faced a new challenge: the demolition of the old Foix Thermal Power Plant, located in Cubelles, Barcelona.

The project, which started in 2017, consisted of the complete dismantling and demolition of the plant, which had been closed for almost two years.

Significant elements included the demolition of the 175 m (574 ft) high chimney stack, the turbine of the generator unit and its building and concrete bedplate, and the complete demolition of the boiler.

Lezama also performed the preliminar y cleaning and management of the waste from the operation of the plant, as well as removing other hazardous waste, including asbestos.

Preliminar y cleaning had to be approved before proceeding to demolition.

The turbine-generator was disassembled avoiding the use of cranes, which reduced risk. For the demolition of the building, the use of heavy machiner y in the removal of the bedplate enabled rapid execution and the complete separation of materials. It was carried out under stringent dust and noise emission control measures.

LONG -ARM MACHINERY

To fulfil the deadlines set for the project, the project management team used innovative equipment, machiner y and techniques. Remote controlled robots and long-arm machiner y were used to demolish the chimney stack, in addition to combining manual and mechanical demolition methods in the metal and concrete structures.

“From a safety standpoint, we reduced the number of crane manoeuvres significantly using different long-arm excavators of various sizes, the largest having a reach of 35 m (114 m),” said David Peral, technical site manager of Lezama Demoliciones.

The nature of the Foix project called for the use of innovative equipment.
ALL PHOTOS: LEZAMA DEMOLICIONES
The Foix Thermal Power Plant in Spain was closed for almost two years before Lezama started on its demolition.

Using robots and long-arm machiner y reduced the number of man-hours of risky work while enabling the complete segregation of waste from an environmental standpoint, removal of asbestos seals in the chimney stack and the interior refractor y brick and the concrete from the shaft.

The impossibility of blasting was also an important conditioning factor for the project, as it required the work to be carried out using manual or mechanical means. This impediment was due to the proximity of a railway line, roads and the nearby urban area.

“Apart from the chimney stack, the boiler was nearly 55 m (180 ft), and the turbine and ancillar y buildings exceeded 25 m (82 ft),” added David Peral.

“Wind control (both in the chimney stack and on the ground) was stringent, requiring stopping certain work at height for safety reasons on many occasions. Monitoring was performed in real time>

ADAPTED PL ANNING

From the environmental standpoint, Lezama even had to adapt to peregrine falcon nesting periods.

This was achieved by adapted planning, avoiding dust-generating work on windier days, for example. Neither did noise-related incidents occur, with 100% of positive results in the controls carried out.

After the successful demolition of the Foix Thermal Power Plant, Lezama embarked on another long-term project.

This was the Anllares Thermal Power Plant, located in Páramo de Sil (Leon) and started in June 2019.

The significant experience acquired at Foix served as a basis for executing this new project successfully, as well as providing an example of implementing improvements in demolition work in terms of quality, environment and work safety.

In this case, Lezama worked with a new company, Naturgy. It was the first demolition project executed for the energy company, which was followed by La Robla and Narcea thermal power plant projects, located in Leon and Asturias, respectively. The Anllares Thermal Power Plant, closed in December 2018, and had a single 365.2 MW thermal generator, jointly owned by Endesa and Naturgy.

EXPLOSIVE DEMOLITION

The plant’s characteristics included a series of elements that represented a major demolition challenge. First, the slender chimney stack and large cooling tower, 150 and 110 m (492 and 360 ft) high, were demolished using explosives.

Next, the boiler, 50 m (164 ft) high and an apparent volume of 177,500 cubic metres (6.2 million cu ft), which was composed of such different materials such as fibrecement, insulation and various metals like iron, stainless steel and copper. This disparity of composition represented a major challenge for the demolition works, since it is essential to separate these materials to make proper use of the waste for recycling.

Lastly, the hopper shed building, with a height of 50 m, had to be dismantled with large-scale machines.

Additionally, dismantling work was carried out on the turbine of the generator set and the concrete bedplate, the building that housed it and the metal structures that connected all these elements to the thermal power plant.

All this work was carried out through the principle of selective demolition – separating the materials at source to minimise the production of waste deposited at landfills.

Anllares Thermal Power Plant was another long-term demolition project for Lezama.

As a result, the preliminar y cleaning of the plant was initially carried out, removing potentially polluting materials such as fuel, diesel, ashes and other power plant products. Furthermore, hazardous waste was extracted, especially asbestos, contained particularly in locations such as the boiler, the inner chimney stack seals or the cooling tower.

REDUCING RISK

In terms of safety, the demolition of the Anllares Thermal Power Plant represented a major step for ward for Lezama. Unlike Foix Thermal Power Plant, where no blasting with explosives took place, in this power plant demolition in Leon there were up to four blasts – silos, chimney stack, cooling tower and boiler – which eliminated the need for work at height and, using the appropriate procedures and ensuring the safety distance, the risk for workers was highly reduced.

Moreover, the use of long-reach and large-scale machines also guaranteed that workers were not exposed to work at very great heights. This was achieved due to the KMC 1200S long-arm excavator, by Japanese manufacturer Hitachi.

In the second half of the project period, Lezama acquired 3D vision equipment and a virtual platform from the company Ludus Global. This tool enables the persons in charge of site safety to provide workers with safety training, creating an immersive and very realistic experience with potential accidents in projects.

David Peral: “Blasting represented a major improvement process, since it offered greater performance both in terms of demolition and in the recover y of materials, and also reduced the risk for workers during the demolition of high-rise structures.”

At Anllares, Lezama worked with energy company Naturgy.

The chimney stack had a diameter at the base of 13 m (42 m) and 7.35 m (24 ft) at the crown. It was made of reinforced concrete and internally lined with refractor y brick distributed in 12 trommels, with asbestos seals, leaving an air chamber between the concrete wall and refractor y brick wall.

Dismantling the refractor y brick lining turned out to be a major challenge from a safety standpoint, and had to be completed before blasting.

Horizontal reinforcements were cut on the outer blast side. Then horizontal cuts were made to reduce the resistance at the rear of the chimney and prevent it from impeding the directional fall. Lastly, the gelatinous dynamite was placed along two-thirds of the perimeter of the chimney, forming a rupture wedge of decreasing height from 2.65 m (8 ft) to 0.6 m (2 ft).

To cushion the fall of the chimney stack, a sand bed was placed on the fall position and water pools with explosives were also prepared, making it possible to trap the dust that raised during the falling process.

Thanks to this technique, the company was able to recover 3,500 t of concrete.

This article appears in January-February 2023

Go to Page View
This article appears in...
January-February 2023
Go to Page View
COMMENT NEW STARTS
It is the start of the year, a
IN CASE YOU MISSED IT
PHOTO: DOOSAN Visit www.khl.com for your daily
STRONG SALES WHAT'S HAPPENING?
OEMs have been releasing their fourth quarter and
WHAT IT MEANS
These results reflect the overall health of the
INTERMAT RETURNS
The Intermat exhibition will be held in Paris,
ICONIC STADUIM UPDATE
PHOTOS: FCBARCELONA.COM The remodelling of the historic
US$5 TRILLION ECONOMIC AMBITION
India aims to become a US$5 trillion economy, but to do so must address infrastructure gaps. Catrin Jones looks at how the country is planning to meet its ambitious goals
POTENTIAL FOR WORLD-LEADING MARKET
India has invested heavily in infrastructure in recent years and that trend looks set to continue as the country looks at moving from a regional power to a global one, writes Scott Hazelton
TALL BUILDINGS, HIGH DEMANDS
To accommodate the world’s growing population cities are building taller buildings, but how does this fit with the global target of increasing the sustainability of infrastructure? Catrin Jones reports
WALKING THE WALK
Bauer Maschinen CEO, Dr. Ruediger Kaub, on the challenges – and opportunities – of electric power and automation
FROM THE EDITOR
I’d like to tell you about some important
McIntosh Power Plant, Florida
PHOTO: TOTAL WRECKING & ENVIRONMENTAL US demolition contractor
2022: The year in quotes
D&RI/JOE MATHER PHOTOGRAPHY Excerpts from inter views and
30 years of the RVA Group
A video interview with managing director and D&Ri
PP O’Connor’s starring role in football stand demolition
PHOTO: WREXHAM AFC While the film industr y
Site Report: Mainline Demolition and the Broun Avenue bridge
PHOTO: MAINLINE DEMOLITION Behind the scenes at the
Tomorrow’s thinking today
Construction and demolition are changing rapidly, leading to observers on both sides of the Atlantic analysing how this will translate into actual equipment manufacturing and deployment.
Demolition – the view from a trainee
Demolition companies are not just focused on the
The starting point
Quick couplers are just one example of excavator at tachments leading to an increasingly safe workplace. D&Ri looks at the latest developments.
In search of new markets
HYDRAULIC BREAKERS Rotair has unveiled a vision to
Lezama’s power plant challenge
How a Spanish demolition contractor drew on 25 years of experience to come up with two dif ferent methods for projects in the energy industry.
‘ Where the future begins’
The 90,000 sq m outdoor exhibition space at
President Panseri’s thoughts for 2023
Despite uncertainty in the demolition sector, EDA president Stefano Panseri is hopeful that the progress made in 2022 will continue.
ACHIEVING PEAK EFFICIENCY
Engine manufacturers have been steadily improving diesel technology, reducing emissions and also improving fuel economy, reports Julian Buckley
'BIGGEST EVER' SHOW
CONEXPO-CON/AGG
THE SKY'S THE LIMIT
Drones are increasing accepted as part of the construction process and their applications for the sector are ever evolving, discovers
TECHNOLOGY'S VALUE PROPOSITION
Technology has the potential to help solve many of construction’s pain points, such as a lack of workers and the need to reduce emissions, ROB PAINTER, Trimble CEO, tells
WHY EQUIPMENT MANUFACTURERS ARE BUYING
Construction equipment manufacturers have been engaged in an arms race to buy up technology firms to make their machines more efficient, more environmentally sustainable and safer, reports
'FUTURE PROOF' AIRPORT
Where is it? Between Warsaw and Łódź, Poland
Looking for back issues?
Browse the Archive >

Previous Article Next Article