Inside the Argyle Diamond Mine Closure Project

How Liberty Industrial dismantled one of the world’s largest diamond mines in Australia’s remote Indigenous Outback.

CLIENT: Rio Tinto

CONTRACT VALUE: AU$53 million

PROJECT DURATION: January 2021 to April 2024

PEAK WORKFORCE: 50

N estled in the East Kimberley region of Western Australia, the Argyle Diamond Mine held a unique place in global mining history. Situated on the traditional lands of the Miriuwung, Gidja, Malgnin, and Wularr people, the mine operated for 37 years, becoming a major global producer of diamonds and the largest supplier of natural-coloured diamonds, including the coveted Argyle pink and red diamonds. Mining ceased in November 2020, marking the start of an extensive decommissioning project to restore the remote site to its natural state.

Site A on the Argyle Diamond Mine Project.

Equipment deployed

EXCAVATORS

1 x Kocurek 200t High Reach Excavator

1 x Volvo EC750HR

1 x Volvo EC750DL

3 x Volvo EC480D

4 x Volvo EC250DL

5 x Volvo EC380D

1 x Volvo EC88

TRUCKS

3 x Volvo A40F

2 x CAT 740B

2 x Volvo Prime Movers

1 x Kenworth Prime Mover

1 x Mack Prime Mover

1 x Isuzu Service Truck

1 x Hino Water Truck

1 x Volvo A30 Articulated Water Truck

1 x Isuzu Hook Bin truck

CRANE

1 x Grove RT9130E All-Terrain Mobile Crane

LIGHT VEHICLES

2 x Buses (Toyota HiAce 11 seater)

11 x Utes (Toyota Hilux 4x4)

MATERIAL HANDLERS

1 x Sennebogen 830M

1 x Liebherr 934 MH

SHEARS

Genesis (GXP990R & GXT665)

Fortress (FS145R)

Box Shear (Squalo 2000)

Covering 50 hectares, the mine sat over 2,800 kilo-metres from Perth, with no major cities nearby. Self-sufficiency was paramount, with the site housing its own airport, accommodation, and operational facilities. Mining activities began with open-pit techniques, reaching depths of 600 metres, before transitioning to underground block cave mining in 2013. The site’s significance extended beyond its resources, with careful planning required to respect Indigenous heritage sites and culturally significant areas. Liberty Industrial worked closely with Traditional Owner businesses throughout the project, fostering a partnership that contributed to waste management, earthworks, and mechanical maintenance services. This collaboration included local engagement initiatives, such as Liberty’s Employment Readiness and Trainee Program, which saw two Indigenous trainees achieve Level 1 certification and secure full-time roles.

DEMOLITION AND REMEDIATION

Following its closure, Rio Tinto commissioned Liberty Industrial to oversee the demolition of all above and belowground infrastructure. This encompassed major structures such as the primary, secondary and tertiary crushers, heavy media separator, diamond recovery building, and material processing facilities. Concrete footings and underground services were removed, while contaminated areas were remediated. Given the site’s isolation, Liberty also constructed and managed on-site landfills, categorised for general and contaminated waste.

Mechanical demolition methods dominated the project, led by Liberty’s fleet of specialised equipment, including a 200-tonne Kocurek high-reach demolition excavator and a 100-tonne Volvo 750 high-reach machine. This heavy-duty equipment allowed for safer operations by reducing personnel exposure.

Induced collapse techniques were applied to high-level conveyors and trestles, with demolition strategies verified using advanced ASI Extreme Loading software. The entire process was guided by rigorous health and safety protocols, including continuous monitoring of noise, vibration, and air quality.

Waste & recycled materials

VOLUME OF TOTAL WASTE: 40,000 CU M

■ 35,000 cu m of contaminated waste disposed of at the site containment cell (including contaminated soils).

■ 5,000 cu m of general demolition waste disposed at the site inert landfill.

RECYCLED MATERIALS:

■ 100,000 cu m of concrete reused on site.

■ 34,000 tonnes of ferrous metals recycled offsite

■ 1,000 tonnes of non-ferrous metals recycled offsite

■ 800 tonnes of HDPE pipe recycled offsite

A notable aspect of the remediation saw the contractor’s in-house civil remediation team remove 30,000 cubic metres of hydrocarbon-impacted soil and dismantle a 30-kilometre asbestos pipeline. Contaminated materials were disposed of in lined containment cells designed to prevent environmental harm and facilitate future revegetation efforts.

SUSTAINABLE RESOURCE MANAGEMENT

The mine’s remote location presented significant logistical challenges for recycling. Transporting materials to Perth (2,800 km away) or Darwin (1,000 km away) was uneconomical due to the vast distances involved. Instead, Liberty leased a section of land next to Wyndham Port, approximately two hours from the mine, to stockpile processed scrap metals and other materials.

From there, 34,000 tonnes of ferrous metals and 1,000 tonnes of non-ferrous metals were shipped in three carefully scheduled consignments – each weighing an average of just over 11,000 tonnes, aligned with the port’s tidal schedule.

In addition, 800 tonnes of high-density polyethylene (HDPE) pipeline was transported to an off-site facility for reuse.

Primary crusher removal.

By maximising material recovery and employing an on-site recycling strategy, Liberty significantly reduced landfill waste, aligning with sustainability goals. All asbestos-containing materials were removed prior to demolition to ensure worker safety and prevent contamination of recyclable materials.

CHALLENGES AND ADAPTATIONS

One of the main challenges encountered by the project team was that the works coincided with the COVID-19 pandemic, which created unprecedented logistical hurdles.

Western Australia’s strict border closures necessitated the relocation of Liberty’s management team and 80% of its workforce to the state. Workers adhered to a three-week-on, one-week-off roster, with alternative accommodations provided to avoid disruptions caused by travel restrictions. This strategy ensured continuity and safeguarded employment for all personnel.

Adding to the complexity, the Kimberley region’s monsoonal wet season brought unpredictable and severe weather, with heavy rainfall and flooding posing risks to accessibility and scheduling. Liberty's team implemented contingency plans to mitigate delays, adapting operations to the region’s harsh conditions.

COMPLETION AND LEGACY

The Argyle Diamond Mine closure was successfully completed on 15 April 2024, within the allocated budget and timeframe. The project’s achievements were recognised with the 2023 Global Rio Tinto Safety Award for Best Contract Partner. Liberty Industrial’s collaborative approach, encompassing strategic planning, advanced demolition techniques, and engagement with Traditional Owners, set a benchmark for sustainable and inclusive decommissioning projects.

Phase 2 of the closure, focusing on residual infrastructure, is anticipated in 2025, ensuring the site’s continued environmental restoration.

This article appears in Jan-Feb 2025

Go to Page View
This article appears in...
Jan-Feb 2025
Go to Page View
CONFRONTATIONAL CONSTRUCTION?
+44 (0)1892 786224 T owards the end
IN CASE YOU MISSED IT
Visit www.construction briefing.com for your daily fix
EUROPEAN GROWTH WHAT HAPPENED?
The European construction sector is expected to see
CALIFORNIA’S AMBITIOUS US$310BN RAIL PLAN
The US State of California – the country’s
BUILDING REAL MADRID'S NEW ROOF WITH LIGHTWEIGHT STEEL
ALL PICS COURTESY: REAL MADRID FC T
STRONG US CONSTRUCTION INDUSTRY EYEING UNCERTAIN FUTURE
The US construction industry has been defiant in recent years despite global economic headwinds hindering other regions. But supreme confidence in the sector is giving way to some worry, Mitchell Keller reports
GROWTH EXPECTED BUT EARLY DAYS
With the Trump Presidency still in its infancy, Scott Hazelton offers his informed estimate about how construction will fare
MOVING EARTH IN ALL SHAPES AND SIZES
The earthmoving industry is known for its massive machines, but Mitchell Keller reports that today’s modern trends and technologies are lending to functional uses for small and mid-sized movers
WHY CONSTRUCTION NEEDS TO STOP FIGHTINH WITH ITSELF
With profit margins tight and some projects not receiving any contractor bids, something needs to change. CICA’s Philippe Dessoy and Juan Armando Vicuna tell Andy Brown that a different approach is needed
DEAR READER,
The start of a new year is always
In case you missed it…
Some of the stories currently online at
South America: A land of opportunity
With growing urban populations, significant infrastructure needs, and a growing awareness of sustainability issues, the region is drawing attention from companies seeking new opportunities. But is South America truly the next frontier for the demolition and recycling sectors?
Emergency demolition at Bunge Bahía Blanca
Precision meets safety: How Grupo Mitre dismantled an agricultural plant, achieving zero accidents and a 100% recycling rate.
Factors influencing largescale demolition in Chile
Demolition leader Grupo Flesan delves into the country’s mining demolition sector, revealing its challenges and future.
Demolition’s global calendar: Trends reflected in 2025 industry events
D&Ri looks at the four most important industry events taking place in the next six months, and what they can tell us about the global industry.
Recycling bridges: How contractors are maximising material recovery
With aging infrastructure driving an increase in bridge demolitions, contractors are focusing on advanced recycling strategies and innovative technologies to maximise material recovery. This article delves into the methods, challenges, and opportunities shaping the industry.
Detaching attachment barriers: Where should a small contractor start?
Discover how the right mindset and smart strategies can help you overcome the costs, risks and logistics associated with owning excavator work tools.
bauma Show time
As the international event returns to its pre-pandemic strength, D&Ri explores what the OEMs have planned.
Embracing sustainability, innovation, and skilled labour in 2025
Stefano Panseri , EDA President, discusses new opportunities for the sector and green demolition practices.
Inside the Argyle Diamond Mine Closure Project
How Liberty Industrial dismantled one of the world’s largest diamond mines in Australia’s remote Indigenous Outback
ON YOUR MARKS GET SET...
With industry behemoth Bauma Munich edging ever closer, we provide a sneak peek at what some of the companies exhibiting will be showing
WHY 2025 COULD BE A BIG YEAR FOR CONTRACTOR ACQUISITIONS AND CONSOLIDATION
The latter half of 2024 saw a flurry of deals to buy construction contractors in the US, involving both institutional and strategic investors. Could 2025 be an even bigger year for investors looking to buy into a promising sector?
A SECTOR PUSHING INEFFICIENCY DOWN
Technology is making drilling and foundations equipment more sustainable and easier to operate than ever before. Andy Brown drills down into the details
CHINA'S CONSTRUCTION OEMS HAVE MADE STRIDES SHOULD WESTERN FIRMS WORRY?
China used to be a lucrative market for Western construction equipment manufacturers but, writes Alan Berger and Robert Droogleever from abcg, the world is changing
A MODEL OF CONSTRUCTION'S NEW NORMAL
Building Information Modelling (BIM) and digital twin processes have been used for decades, but modern technological capabilities have made the assets more valuable today. MITCHELL KELLER reports on the burgeoning market
INCREASING THE HEIGHT OF A 70-YEAR OLD DAM
Gross Reservoir in Colorado, US, is a vital water source for the inhabitants of the state’s largest city, and it’s currently undergoing a major project to increase its height by about 40m. Mitchell Keller asks why this 70-year-old dam is getting a literal lift, and how it’s happening
BATAAN-CAVITE INTERLINK BRIDGE
I n the Philippines, the Bataan-Cavite Interlink Bridge
Looking for back issues?
Browse the Archive >

Previous Article Next Article
Jan-Feb 2025
CONTENTS
Page 58
PAGE VIEW