THE CHALLENGES OF BUILDING SYDNEY'S MEGA METRO

The latest phase of Sydney’s multi-billion dollar metro system is set to open in August, allowing passengers to whizz under the city’s iconic harbour in driverless trains in a matter of seconds. Josh Watkin, Sydney Metro head of delivery, tells Lucy Barnard about the construction challenges his teams have faced building it

With a single toot of its horn, the sleek, white, driverless metro train slides slowly away from Victoria Cross station in Sydney before seamlessly accelerating and racing under the city’s famous harbour at speeds of up to 100km (62 miles) per hour.

Welcome to the latest phase of Sydney’s new Metro megaproject, due to open to passengers on 4 August 2024, with turn-up-and-go computer driven trains crossing the world’s largest natural harbour every four minutes in peak periods.

Designed to better connect north and south Sydney, which are cut off from each other by the harbour, and ease congestion in Australia’s most crowded city, Sydney Metro is one of the world’s biggest suburban rail projects.

“Sydney Metro is Australia’s biggest public transport project and is revolutionising how Australia’s biggest city travels,” says Josh Watkin, head of project delivery at Sydney Metro. Watkin leads a 220-strong team responsible for key elements of these projects including cost estimating, cost management, planning and programming, risk management and reporting.

“Metro is a turn-up-and-go service. With a train every four minutes in the peak in each direction, there is no timetable – people can just turn up, catch the next metro train and be on their way to their destination.”

A former officer in the Royal Australian Navy with a Master’s degree in Peace and Conflict studies from the University of Sydney, Watkin joined the Sydney Metro project back in 2015 as a director for strategy and governance and, in the nearly a decade since, has worked across pretty much every element of the project.

A drone shot of the arrival of a cutterhead TBM
Excavation work in Sydney Bay
PHOTO: SYDNEY METRO

Tunnelling under Sydney Harbour

One of the biggest engineering challenges of delivering Sydney Metro through the city, he says, was how to get under the harbour, which forms a bottleneck.

Before the Metro tunnel, the only way to cross the harbour was the iconic 1930s built Sydney Harbour Bridge and the Sydney Harbour Tunnel dual carriageway which was completed in 1992.

Moreover, as Sydney Harbour Tunnel is an immersed tube tunnel, sitting in a trench in the seabed, the metro tunnels were the first in the Australian city to be drilled into the sandstone, clay, silt and sediment under the harbour, reaching 40m below sea level at their lowest point.

Construction teams used a specially designed 975 tonne mixshield Herrenknecht tunnel boring machine (TBM) named Kathleen to cope with the high pressures while, before they could start work, her 50-strong crew had to undergo training in a hyperbaric chamber simulating the conditions observed by a doctor.

After injecting high grade cement into the sandstone to stop water seeping through the bedrock, Kathleen’s crew first drilled one 884m-long passage from the new Barangaroo metro station to Blues Point in 2019 before the machine was pulled back along the same route and set to work drilling a second 884m-long twin close by.

Australia has numerous mega projects taking place, such as Sydney Metro
PHOTO: ADOBE STOCK

“It was the first time railway tunnels were built under Sydney Harbour, which required specialised TBMs for the unique geological conditions under Sydney Harbour,” says Watkin.

Another of the headline grabbing engineering feats included in the construction of the megaproject has been the creation of Australia’s largest underground railway cavern. The cavern at Victoria Cross station in north Sydney is 300m long, 25m wide and 16m high. By contrast, St Peter’s in the Vatican, the largest church in the world, measures just 218m in length.

Australia’s largest station cavern

The station was difficult to build because the land above it lies uphill compared with the harbour which is 1.5km away. Design teams were caught on the horns of a dilemma: Build the station deep enough to reduce the gradient of the track between the harbour and the station, which would have meant that station had to be built up to 60m below the surface – too deep to install escalators – or reroute the metro line.

In the end the teams chose to re-route and build an additional station at Barangaroo, leaving Victoria Cross just 31m beneath street level. Construction of the cavern started in 2021 and took a team of more than 5,000 people three years to deliver, design and construct. Added to this, Watkin and his teams have had to deal with the additional challenge of constructing Australia’s biggest public transport underneath the country’s bustling financial and economic hub, its central business district (CBD).

In order to minimise disruption and reduce carbon emissions, construction teams removed spoils via barge across the harbour, station construction was staggered to reduce traffic congestion and acoustic sheds were used to contain noise on a number of work sites. “The new Sydney Metro City & Southwest project was constructed in the heart of the bustling Sydney CBD which meant working around noise conditions, limited work zones, and an increase in heavy vehicles through CBD streets, all while respecting the functional needs of the city,” Watkin says.

The megaproject, which by 2032 will comprise 113km of new metro rail and 46 new stations, is actually made up of three new rail lines which are currently under construction: City & Southwest; the Western Sydney Airport line; Sydney Metro West; and one operational line, the Metro North West Line.

The latter, a 36-kilometre track has been in operation since 2019 and stretches all the way from Chatswood in north Sydney to the city’s northwest suburbs.

It was completed by teams of contractors – including Brisbane-based mining services company Thiess, Melbourne-based John Holland, Spanish contractor Dragados and Italian contractor WeBuild – at an impressive A$500 million (US$339 million) under budget and ahead of schedule.

Why is it over budget?

However, the Metro North West is something of a rarity. According to a statement by the incoming Labour government for New South Wales in 2023, the Sydney Metro project as a whole is already A$21 billion (US$14 billion) over its budget.

Construction work at Martin Place, north site
PHOTO: SYDNEY METRO

For the City & South West line, which will eventually run from Chatswood in North Sydney, under the harbour, south to Sydenham and then make its way west to the suburb of Bankstown, costs increased by A$9billion (US$6 billion) to nearly double their original estimate to stand at A$20.5 billion (US$13.8 billion).

The line, part of which will open in August, is the work of teams including John Holland, Italian construction company Ghella, CPB Contractors and British-based Laing O’Rourke. The second part of the project, which requires a conversion of the existing T3 heavy rail line to Bankstown, has been delayed until at least September 2025.

Sydney Metro West, a 24km underground metro railway between Sydney CBD and its planned second CBD Parramatta to the west, had originally been announced with a A$16 billion (US$10.8 billion) price tag and a completion date of 2028 is now targeting a completion date of 2032.

It has overrun initial estimates by A$12 billion (US$8 billion) to stand at A$25 billion (US$16.9 billion) and is currently being built by teams from contractors including Spanish-based Acciona, Dutch headquartered Ferrovial, Malaysian-based Gamuda and Laing O’Rourke.

The A$11 billion (US$7.4 billion) Sydney Metro-Western Sydney Airport Line connecting the city’s new Nancy Bird Walton airport with the existing St Mary’s interchange is said to be running on time and on budget with a scheduled completion date of 2026. However, a report by Infrastructure Australia published three years ago found that the cost of building the airport line outweighed its benefits by A$1.8 billion (US$1.2 billion). The project is currently being built by teams from contractors including Webuild, CPB and Ghella. Tunnelling work has been completed and crews are starting to fit out the stations. Watkin, attributes many of the delays and cost overruns to the Covid pandemic and describes navigating the megaproject through these unprecedented times as both “beyond remarkable” and “deeply rewarding.”

While other sectors of the economy, such as tourism, retail and hospitality, were shut down during the pandemic, big infrastructure projects such as Sydney Metro were allowed to stay open by introducing strict social distancing rules including increased cleaning schedules, temperature checks at the start of each shift and segregating workers into smaller groups with staggered meal breaks.

Project challenges

Moreover, as with many other construction projects taking place during the pandemic, Sydney metro was also hit by materials shortages which led to hikes in the cost of commodities such as iron and steel as well as long waiting times for them to be delivered. “The Sydney Metro City & Southwest project was at peak construction when the pandemic hit that resulted in price escalation in materials and labour as well as delays to programme,” he says.

On top of the supposedly once-in-a-lifetime event of the pandemic to deal with, the Sydney Metro construction teams also have had to deal with a full range of other issues.

These included some of the worst floods recorded in the city in more than 60 years and industrial action by rail workers, some of whom refused to shut off the electricity along the line preventing contractors from accessing existing tracks.

“Work to upgrade the T3 Bankstown Line to metro standards has been impacted by a range of well-documented other external factors that have affected infrastructure projects across the world over the past three years, including poor weather, supply chain and materials issues, and reduced availability of contractors in a busy construction market,” Watkin says.

Workers prepare track
PHOTO: SYDNEY METRO
This article appears in July-August 2024

Go to Page View
This article appears in...
July-August 2024
Go to Page View
ALL SYSTEMS GO
EDITOR Andy Brown andy.brown@khl.com +44 (0)1892 786224
IN CASE YOU MISSED IT
Visit www.construction briefing.com for your daily
ELECRIC EQUIPMENT
WHAT HAPPENED? Electric equipment has been one of
CULTURAL CONSTRUCTION TOPS US$8 BILLION
PHOTO: ADOBE STOCK A new report has revealed
BAM RESTORES ANTARCTIC RUNWAY
PHOTOS: BRITISH ANTARCTIC SURVEY AND BAM Contractor BAM
THE TIMES ARE CHANGING
China has overseen rapid development, which has led to many of the country’s construction contractors and OEMs grow into world-leading companies. With most of that development now complete the future is likely one of slower growth but with a focus on technology, writes Andy Brown
HOUSING SECTOR CONTINUES TO STRUGGLE
Issues with the property sector remain, but infrastructure spending and China’s competitive advantage in solar, battery and EV tech are bright spots, writes Scott Hazelton
GROWTH YET AGAIN
The ICON 200 has seen a number of years of strong sales, and the latest table is no exception
CONCRETE'S EVOLUTION AS A CONSTRUCTION MATERIAL
Still the second-most used substance behind water, global concrete consumption is showing no signs of falling. However, as Mitchell Keller reports, the material isn’t what it once was, as the industry races to create more sustainable products
(MORE) GREAT CHANGE IS COMING
XCMG is China’s largest construction OEM by sales. Mr. Yang Dongsheng, Chairman of XCMG, sat down with Andy Brown to talk about the changing Chinese market, export plans, electric equipment and heavy construction robots
QUIET BUT POWERFUL
Drilling and foundation machines are getting bigger and faster. But, as Mitchell Keller reports, despite their size and speed, today’s equipment is smarter and quieter than ever
THE CHALLENGES OF BUILDING SYDNEY'S MEGA METRO
The latest phase of Sydney’s multi-billion dollar metro system is set to open in August, allowing passengers to whizz under the city’s iconic harbour in driverless trains in a matter of seconds. Josh Watkin, Sydney Metro head of delivery, tells Lucy Barnard about the construction challenges his teams have faced building it
HOW TO MAKE THE MOST OF BIM
Working smarter, not harder, is the goal and BIM is here to help. KATHERINE WEIR compiles a collection of case studies showing how successful this technology can be in construction
A REVOLUTION IS COMING
With 12 brands under his control, YVES PADRINES, CEO, Nemetschek Group, is a man with his finger on the pulse of technology trends and opportunities, ANDY BROWN discovers
IS CONSTRUCTION UNFAIRLY BLAMED WHEN PROJECTS GO WRONG?
Are construction companies an easy target for politicians and the wider public when projects go wrong? Neil Gerrard speaks to Professor David Edwards to find out if the industry is getting a raw deal
WORLD'S MOST POWERFUL TELESCOPE READY FOR CONSTRUCTION
What is it? The Giant Magellan Telescope Where
Looking for back issues?
Browse the Archive >

Previous Article Next Article
July-August 2024
CONTENTS
Page 42
PAGE VIEW