COPIED
7 mins

THE CHALLENGES OF BUILDING CALIFORNIA HIGH-SPEED RAIL

Garth Fernandez, Central Valley regional director for the California HighSpeed Rail Authority, tells Neil Gerrard what some of the mostchallenging aspects of the multi-billion-dollar megaproject are, where construction stands, and what work is still to come

Working at height on the Cedar Viaduct
ALL IMAGES: CALIFORNIA HIGH-SPEED RAIL AUTHORITY

California High Speed Rail will be the first fully electrified high speed rail system in the US when it finally enters service.

The plan, when California voted in favour of a US$9 billion bond authorization back in 2008 to kickstart construction, was that the completed line would whisk passengers from Los Angeles to San Francisco within two hours and 40 minutes.

Some 15 years later, 119 miles of the line are under construction, spread over five counties in California’s Central Valley. Work is also underway to advance design for the project to run the 171 miles from Merced to Bakersfield. That would cost an estimated US$35 billion and launch as early as 2030.

However, the prospect of building the full line between the Bay Area and Los Angeles remains, at the moment – a vision for the future, rather than a reality. It emerged earlier this year that the cost of building the railway in its entirety could cost a monumental sum of money – between US$88 billion and US$128 billion. When the project was approved in 2008 the estimated cost was approximately US$33 billion and it was expected that the service would be up and running by now.

The challenges

Garth Fernandez, Central Valley regional director for the California High-Speed Rail Authority explains that the megaproject came with several challenges. He splits these into four areas: The requirement to follow existing transportation corridors; the project not being fully funded; lack of a consistent, reliable funding source; and the need to execute new agreements with all local agencies, regulatory agencies and utility companies.

Spending on the project so far (as of May 2023) is in the region of US$10 billion, with most of that coming from the State of California. To get it completed in full will require federal funding and the Authority revealed earlier this year that it planned to obtain large new grants from the Bipartisan Infrastructure Law (BIL) to move the project further forward.

One of the many bridges that have been constructed as part of the project

Every project I have worked on was unique and came with its personnel and technical challenges. This project is no different in that regard, as you could look at it as delivering several projects

California recently won US$202 million in federal funding for grade separation projects and is seeking a further US$8 billion in grants over five years. However, at the end of October, it emerged that the Republican-led US House of Representatives planned to vote on legislation that would bar the Biden administration from awarding more funds to the project.

As far as work on the project so far is concerned, there are nearly 30 active construction sites currently, with 40 structures in the Central Valley already built. More sites are due to break ground over the next several months.

A Caterpillar excavator works at the Tulare-Street-Underpass

WHO IS BUILDING CALIFORNIA HIGH SPEED RAIL?

In the Central Valley, there are 119 miles of track currently under construction, spread over five counties. Those 119 miles are divided into three design-build construction packages:

Construction Package 1 comprises 32 miles of line spanning from Avenue 19 in Madera County to American Avenue in Fresno County. This construction package is being built by Tutor-Perini/Zachry/Parsons. The 32 miles includes several grade separations and large viaducts including the completed San Joaquin River Viaduct and Cedar Viaduct, featuring single- or double-span arches respectively.

Construction Package 2-3 is 65 miles long and is the largest construction package. It begins at the terminus of Construction Package 1 and stretches to a mile north of the Tulare-Kern County line. Dragados-Flatiron joint venture is the design builder. Multiple grade separations will be built across some of the rural parts of Fresno, Kings and Tulare counties. This Package is also home to the largest high-speed rail structure, the Hanford Viaduct, which spans more than 6,300 feet (1,920 metres) long.

Construction Package 4 is 22 miles long from a mile north of the Tulare-Kern County line to Poplar Avenue, just north of the city of Shafter in Kern County. Design build contractor California Rail Builders is a joint venture of Ferrovial-Agroman West, LLC and Griffith Company. It will be the first completed construction package in the Central Valley, anticipated to be done by the end of 2023.

Fernandez says, “The most challenging aspect was being in construction ahead of property acquisition. Our project within the 119 miles needed to acquire around 2,300 properties to construct. We are also relocating more than 1,800 utilities ranging from telecommunications, electric, gas, water, and sewer that needed to be done in advance of completing the major infrastructure elements. “One of the challenges was that the scope of work was not fully defined when the project was advertised. Most agreements with local agencies, regulatory agencies, and utility companies were not executed at the time of advertisement, thereby creating additional requirements and restrictions from the owners, constrained work windows and added scope as these were finalised. All of this resulted in significant scope modifications, a need for acquiring several more properties resulting in cost and schedule challenges.”

Nonetheless, Fernandez says there had since been “great progress” in executing agreements with the high-speed rail corridor now fully designed to establish scope.

He says the acquisition process is now 97% complete, with a “handful” of acquisitions remaining and several utilities yet to be relocated. “Property acquisition and resolving land rights is a diminishing risk that will remain until all utilities are relocated,” he asserts. Fernandez, who has 30 years’ experience in project delivery and has worked on projects both as a designer and construction project manager, adds, “Every project I have worked on was unique and came with its personnel and technical challenges. This project is no different in that regard, as you could look at it as delivering several projects.

“However, working on the high-speed rail mega project has presented unique and complex challenges due to the immense scale, substantial budget, extended timelines, and a high level of complexity on account of the interaction between the various functional elements.

“Collaboration between the several large teams, substantial labour and material needs, robust risk planning and management, and agility are key elements to the success of the program. The margin of error is small, and the cost or schedule impact associated with an error or mistake could be severe, necessitating a heightened focus on execution and the ability to navigate through unforeseen obstacles.”

Nonetheless, Fernandez says the team at the Authority is “highly motivated, confident, determined, and integrated”.

He adds that, “We have learned from several mistakes and are driving towards our aggressive but attainable goal to have an interim operational segment in the Central Valley in the 2030 to 2033 timeline.”

Innovative techniques

Work underway at the moment involves the heavy civil infrastructure of the project, comprising 115 structures, over 200 wildlife crossings and the placing of over 24 million cubic yards of earth. Construction of a 35-mile intrusion protection barrier is also underway.

Despite challenges, Fernandez says there had since been “great progress” in executing agreements with the high-speed rail corridor now fully designed to establish scope

To assist in the construction, there is a concrete pre-casting facility at Hanford that produces all of the California Wide Flange girders (adopted by Caltrans as a standard section in 2012), as well as deck panels and piles for construction package 2-3. The facility is also pre-casting tub girders for various viaducts on site.

Meanwhile, contractors are using Tier 4 construction equipment to reduce the amount of pollutants released during construction. In the future, the Authority will require future contractors to utilise 100% zero-emission fleets, although it did not indicate when this requirement will be introduced.

Project legacy

The Authority recently approved the release of a Request for Qualifications for electrified high-speed trainsets. This trainset procurement process will allow the Authority to procure six trainsets capable of operating at 220 mph, with two prototypes due for trial running in 2028, ahead of four additional trainsets by the end of 2030 to support revenue operations on the 171-mile Merced to Bakersfield section.

The project has thus far created more than 11,000 jobs

Last year, the Authority announced it would be restructuring its track and systems procurement due to high inflation, supply chain challenges and economic climate. It is in the process of re packaging by selecting procurement methods that provide more flexibility and innovation.

Despite the significant challenges involved, Fernandez says, “I am confident that once complete, the California High Speed Rail system will provide an alternative mode of transportation that is sustainable, faster, clean and energy efficient.”

He reveals that the project has so far created more than 11,000 jobs, with 70% of those going directly to people from the Central Valley.

“We’ve been able to keep these jobs close to home; some of these workers having to commute only 20 to 30 minutes. While I can’t speak for all of them, I can say personally I’ve heard from several who are glad to work close to home and proud to work on such a historic transportation project,” he concludes.

For more articles like this make sure that you subscribe to the Construction Briefing, KHL’s daily newsletter that offers concise, comprehensive coverage of key issues, best practices, and expert comment on the industry. www.international-construction.com

This article appears in November-December 2023

Go to Page View
This article appears in...
November-December 2023
Go to Page View
COMMENT
IT IS NEVER BORING…
LEGAL BATTLE
WHAT HAPPENED? The Association of General Contractors (AGC)
IN CASE YOU MISSED IT
Visit www.khl.com for your daily fix of
TBM BREAKTHROUGH
Herrenknecht has reported that the contractors working on
TWO NEW TOWERS PLANNED FOR SAUDI ARABIA'S NEOM
Two new towers aimed at attracting tourists to
NEW CHALLENGES AHEAD
Argentina has secured finance to develop its infrastructure, but a new President may have different plans. Catrin Jones looks at what the future for construction might hold
CHALLENGING MARKET CONDITIONS
With high levels of debt and low investment the economic picture looks problematic, with construction seeing limited or even negative growth, writes Scott Hazelton
A CIRCULAR (ROAD) ECONOMY
Manufacturers in road construction are thinking green when it comes to materials and alternative fuels. The journey to net zero is underway, and the developments in equipment and tech are increasingly advanced, reports Katherine Weir
A GLOBAL VIEWPOINT
There aren’t many better placed to ask about the challenges and opportunities facing construction than Caroline Gumble, CEO, CIOB. She talks to Andy Brown about the skills shortage, sustainability and more
WHEELS OF INDUSTRY
Construction is working hard to innovate and adapt its wheeled loaders, but what’s next in their evolution? Catrin Jones looks at how manufacturers are getting ahead of the curve
FROM THE EDITOR
Well, here we are, at the end of
In case you missed it…
Some of the stories currently online at www.demolitionandrecycling.media
The biggest demolition event of the year – in pictures!
The 15th World Demolition Summit and Awards returned to North America in 2023, taking place in Canada for the first time.
Purchase decisions: Redefining ‘return on investment’
D&Ri looks at the latest crushing and screening advancements, and at how purchase decisions are changing.
Time to invest?
A significant rise in the value of the d&ri100 compared to a year ago prompts a number of demolition contractors to capitalise on the sector’s recent growth by investing.
Applying the rule of three to dust suppression
Are we doing enough to tackle fugitive dust?
EDA, committed to recognizing the talent in the demolition industry
As the International Media Partner of the European Demolition Association (EDA), Demolition & Recycling International brings you the latest update, from EDA President Stefano Panseri.
Decommissioning: the end, or the start of a new beginning?
In his last column for D&Ri, Richard Vann, Managing Director at RVA Group, reflects on the importance of learning and sharing knowledge.
THE CHALLENGES OF BUILDING CALIFORNIA HIGH-SPEED RAIL
Garth Fernandez, Central Valley regional director for the California HighSpeed Rail Authority, tells Neil Gerrard what some of the mostchallenging aspects of the multi-billion-dollar megaproject are, where construction stands, and what work is still to come
IS CONNECTIVITY THE FUTURE OF CONNECTED CONSTRUCTION?
There are clear advantages to a connected construction site. CATRIN JONES investigates what such a future could look like, and the barriers preventing the industry from achieving this
ELECTRIFICATION SAFETTY AND GAME-CHANGING TECH
Alexander Greschner, Chief Sales Officer, Wacker Neuson, highlights their current – and future – direction to Catrin Jones
CAN DREAMS OF A NEW INDIA-MIDDLE EAST-EUROPE CORRIDOR STAY ON TRACK?
Ambitious plans could see the construction of high-speed rail links across the Arabian Peninsula to form the backbone of a multibillion trade corridor designed to link India to Europe, Lucy Barnard reports
WHAT'S THE FUTURE OF TRADE SHOWS
With the pandemic and remote tools changing the world forever, Neil Gerrard examines how construction equipment shows are changing to cater for the shifting demands of attendees
CONSTRUCTION FOR ANTARCTIC 'FIRST' RESEARCH STATION
PHOTO: BAM Where is it? Antarctica When will
Looking for back issues?
Browse the Archive >

Previous Article Next Article
November-December 2023
CONTENTS
Page 59
PAGE VIEW