BUILDING THE WORLD'S MOST COMPLICATED REACTOR

ITER is where science and construction meet the future as an international team build a reactor that harnesses the power of the sun, reports

An aerial view of the 180 hectare site of the International Thermonuclear Experimental Reactor (ITER) project
ALL PHOTOS: ITER

Aeureka moment is on the horizon for science and for global energy. Before that happens, however, a large and complex construction project must be completed and, like most mega-projects, it is over budget and delayed.

The project is ITER (the International Thermonuclear Experimental Reactor) and is being built in southeastern France. Construction began in 2010, with an estimated completion date of 2018. Now, it is unlikely that the reactor will be operational before 2030. The roots of ITER, however, go much further back. Given today’s geopolitical situation, it seems hard to believe that it was jointly brought to life in 1986, by US President Ronald Reagan and Soviet General Secretary Mikhail Gorbachev.

The pair said the project should be delivered “…for the benefit of all mankind.” If it succeeds in its mission to deliver a tenfold return on power input (ie 500MW of fusion power output from 50MW of input heating power), it will have proven fusion’s potential to revolutionise the global energy landscape.

Visiting the ITER project is a very different experience to taking a tour of a more traditional nuclear power plant. It’s not so much the new science that leaps out at you – although the science is without doubt at the most cutting of edges – but rather the sense of the facility being a global village.

It’s certainly an example of how national borders can be overcome. The facility’s openplan offices, corridors and cafeterias buzz with the sound of scientists from around the world discussing best practices and next steps for the delivery of energy from nuclear fusion.

What’s more, the ITER footprint is big – spanning a 180 hectare site – which makes it hard to process the fact that this is merely an experimental facility. It certainly feels as though something world-changing is happening here.

Metrology is involved in every step of ITER machine assembly, including the repair works underway on critical components

The tokamak

At the heart of ITER is the tokamak reactor, which will play host to the same fusion reactions that take place at the centre of our Sun. The reactor will use incredibly large magnets to confine superheated spinning plasma.

The plasma will reach a mind-boggling 150 million degrees Celsius (at least ten times hotter than the Sun) and, as it spins, the deuterium and tritium atoms within it will collide, causing their nuclei to fuse together.

The energy created from this fusion is far greater than the splitting of atoms, which takes place in today’s nuclear reactors.

Another benefit of fusion is that it’s far cleaner than fission and less dangerous. While the process does create radioactive waste, it has a hazardous half-life of only 12.3 years. From a safety perspective, reactions within the tokamak rely on the continuous input of fuel, so if for some reason the power input is withdrawn, the machine simply ‘switches off’. The purpose of the project, of course, is to prove the science at scale and only once that is done can work begin on establishing nuclear fusion as a realistic power source for the future.

Vacuum vessel bevel repair will be carried out at the ITER site by a consortium called SIMANN comprising the Italian firms SIMIC and Ansaldo Nucleare
In the ITER Assembly Hall, metrologists from the SIMANN (SIMIC-Ansaldo) consortium are performing ultra-precise measurements on the bevel joint region of vacuum vessel sector

As ITER’s communication officer, Sabina Griffith, says, “Size matters in fusion. You need to have a certain volume; an amount of molecules and atoms in there [the tokamak], to have enough reactions to create a lot of electricity and heat.

“ITER is the project that has to prove that we can do it on an industrial scale.”

Put simply, the goal of ITER is to generate 500MW of thermal output for one hour. Once that is achieved, the race will truly be on – around the world – to change the face of global energy and possibly help bring the planet back from the brink of a climate catastrophe.

Construction challenges

The nature of ITER’s set-up should mean there is no need to generate international excitement about nuclear fusion – 35 nations are already emotionally (and financially) invested.

Unfortunately, while ITER is a tremendous global collaboration, its egalitarian set-up may at times have hampered its progress.

Checks and balances, for example, take time in both the undertaking and the ratifying – especially when precision components are being manufactured in so many different countries. The challenges of the construction process were somewhat exposed during the Covid pandemic, when it became exponentially more difficult to send scientists and engineers around the world to carry out quality checks.

Late in 2022, it was announced that defects had been detected in the thermal shields that were manufactured during Covid. These shields will insulate the super-cold superconducting magnets from the super-hot plasma inside the tokamak.

Cracks in thermal piping were found; cracks so small they had to be identified using X-ray tomography, which was developed in collaboration with research engineers at CERN in Switzerland.

Ultimately, some 23km of piping has had to be replaced. ITER bosses warned that consequences “would not be insignificant”, and the full ramifications in terms of ITER’s delivery are still unknown.

Installing a million components

The good news is that challenges and setbacks are, up to a point, one of the benefits of an experimental reactor.

At the time, the director general of ITER, Pietro Barabaschi, said, “The know-how we are acquiring in dealing with ITER’s first-of-a-kind components will serve others when they launch their own fusion ventures.”

It’s also fair to say that, when a project involves the installation of more than a million components, there are going to be one or two bumps in the road.

ITER’s communication officer, Sabina Griffith explains why it is taking so long to build. “These are first-of-a-kind components; nobody has done this before,” she says. “We are playing with mother nature’s forces, so we have to do everything with the greatest care.”

Alongside the attention to detail required to ensure the success, there are the logistical issues that come with any such multinational project. Components are constantly arriving at ITER from all over the world – and Griffith describes one component in particular that must be handled with the utmost care.

“The central solenoid, which is the big magnet at the centre of the machine, will be made of six modules; three are already here, with three more still to come,” she says. “The superconductor is coming from Japan; it will be shipped to San Diego, to General Atomics, and they will turn it into the magnet.”

Griffith concludes, “This is going to be the strongest magnet mankind has ever built. With a [magnetic field] strength of more than 12 Tesla. It has the stored energy to lift two aircraft carriers…It should be bolted together very carefully.”

That sounds like a very large understatement.

Next-level precision

One of the engineers who will be responsible for overseeing much of the ‘bolting together’ of ITER is Laure Navarro.

Since she joined the project – three months before Covid lockdowns in Europe – she says the construction learning curve has been steep. “Sometimes we have tolerances of less than 1cm to place a massive component,” she says. “These are things that require metrology and we have a lot of metrology experts at ITER. “So, the positioning of things in space is very precise and a lot of technology is required to integrate everything.”

There are many never-before-seen components. Many of these will bring unique lifting and manoeuvring challenges, not just because they are large and heavy, but through their unorthodox centres of gravity.

Flags of the seven ITER Members, and the ITER Organisation, stand out against the imposing facade of the tokamak complex

“The biggest single element we put in the tokamak was a lift in 2020… it was 1,250 tonnes, in one piece. We have massive 1,500 tonne overhead cranes in the assembly hall. These are the ones lifting and travelling with the biggest components,” Navarro says. “We learned a lot the first time we used the crane with a real component… about its capabilities, in terms of accuracy and speed and what to expect as a standard duration for a lift. That first lift was actually 20 hours in total, so it helped a lot with our understanding of how the crane reacts.”

Tools for the job

“On the sector module lift, which was not so heavy but critical, it was also very interesting, because you have two centres of gravity [on the component], so you need to be able to monitor the gaps between the two shells and integrate them. “For sure, every time you learn.”

Navarro adds, “We and the contractors have developed tools specifically made for the purpose of ITER construction. In fact, we have more purpose-built tools than regular tools for the assembly of the tokamak.”

Describing the machine as “like giant Lego,” Navarro plays down the engineering challenges of moving huge components into positions with critical accuracy.

“We have plenty of mobilisation tools in 3D to show us how we need to assemble it,” she says. “We use laser scanners that help position with targets, and we have sensors to measure gaps.”

She adds, however, that, “Having a colourful 3D video is nice, but when you see the components in reality and you have to move them around, this is something else.

“Sometimes it’s more hands-on pragmatic experience that works – sometimes just having a vertical line with gravity is sufficient.”

Hopefully there are no more major bumps in the road for ITER and that it proves the science of fusion for power. It will be the first reactor to produce more heat than is input and could lead the way to safe and clean energy. iC

This article appears in March-April 2024

Go to Page View
This article appears in...
March-April 2024
Go to Page View
IS THE INDUSTRY READY FOR A DISRUPTOR?
We recently hosted our first-ever in-person Construction Technology
IN CASE YOU MISSED IT
Visit www.construction briefing.com for your daily
EQUIPMENT SALES
WHAT HAPPENED? Off-Highway Research has announced its predictions
$2.6 BILLION AIRPORT EXPANSION IN SPAIN
PHOTO: ADOBE STOCK Plans have been unveiled to
ROAD CONSTRUCTION PROJECT IN THE HIMALAYAS
India’s most ambitious tunnel construction project is currently
THE PURSUIT OF CARBON NEUTRALITY
Despite unforeseen challenges, some of the country’s largest contractors have reported positive results as the country recovers from the pandemic
CHALLENGING CONSTRUCTION CONDITIONS
French construction remains in recession although growth in the medium term should come from the €100 billion ‘France Relance’ plan, writes Scott Hazelton
LOOKING UP - GLOBAL HIGH-RISE CONSTRUCTION TRENDS
Worries over financing, liquidity in some regions, and meeting sustainability seem to be lessening as the planet’s urban centres keep building into the sky, Mitchell Keller reports
A RETURN TO PARIS
Intermat’s organisers have shortened this year’s trade fair to four days, aiming to save energy and reduce emissions
BUILDING THE WORLD'S MOST COMPLICATED REACTOR
ITER is where science and construction meet the future as an international team build a reactor that harnesses the power of the sun, reports
A MARATHON NOT A SPRINT
From state-of-the-art laser scanning and drone-based mapping to advanced geospatial data analytics, CATRIN JONES looks at surveying’s development
WHY CONSTRUCTION IS'TIRED' OF SEEING TECH THAT ISN'T AVAILABLE TO USE
ANDY BROWN talks to DR BURCIN KAPLANOGLU, vice president of innovation and co-founder of Oracle Industry Labs, about how it is using its labs to understand what technology the industry can use in the here and now
WILL AMERICA'S BIGGEST-EVER CIVIL ENGINEERING GET STARTED?
Costs are ballooning for the Coastal Texas Project – commonly called the ‘Ike Dike’ – and at US$57 billion, some are concerned the coastal barrier may never get built, reports
WHY ARE MINI EXCAVATORS INCREASING IN POPULARITY?
The mini, but mighty, machines are continually growing in popularity. Catrin Jones takes a look at some of the newest developments and what is next for the well-loved compact machine
BUILDING THE UK'S 'MOST SUSTAINABILE' LIVE ENTERTAINMENT VENUE
Where is it? Manchester, UK When will it
Looking for back issues?
Browse the Archive >

Previous Article Next Article
March-April 2024
CONTENTS
Page 26
PAGE VIEW